rip woods.jpg
ENVIRONMENTAL REVIEW

The University of California is required to comply with the California Environmental Quality Act (CEQA).  The scope of University activities that may be subject to CEQA is very broad.  The following description pertains to CEQA compliance for capital projects.

Purpose (from UC CEQA Handbook)

"CEQA was conceived as a means to require public agencies to consider and disclose to the public the environmental implications of their actions….CEQA imposes an obligation to  implement mitigation measures or project alternatives to mitigate adverse environmental effects, if these measures or alternatives are feasible.  Thus, CEQA establishes both a procedural obligation to analyze and make public adverse physical environmental effects, as well as a substantive obligation to mitigate impacts."  

Environmental Impact Report (from UC CEQA Handbook)

"Probably the best known element of CEQA is its requirement that public agencies must prepare an Environmental Impact Report (EIR) whenever a proposed project may cause significant effects on the environment.  As stated in CEQA Section 21002:1:  The purpose of an EIR is to identify the significant effects of a project on the environment, to identify alternatives to the project, and to indicate the manner in which those significant effects can be mitigated or avoided."

"In a practical sense, EIRs serve other important functions in addition to meeting the legal requirements of CEQA. EIRs, although largely technical documents focusing on the physical environment, are intended to provide an opportunity for the public to participate in the decision-making process for proposed projects, and to provide the public and decision makers with full information about the impacts of a project. Thus, the EIR process serves as a framework for public dialogue about the adverse impacts, as well as the merits, of proposed projects. "  

However, a full EIR is not always required, even for major capital projects. For example, if a project conforms to the 2020 Long Range Development Plan, and if the potential impacts of the project were fully anticipated and analyzed in the master or ‘program’ EIR prepared for the 2020 LRDP as a whole, the CEQA process for such a project can often be more focused and less extensive. The required CEQA process for each project is determined by PEP in phase 3 of the project approval process.

CEQA Process and Milestones

The CEQA process is prescribed by state law and shaped by regulatory time periods: the schedule cannot be compressed and is often lengthened in response to complexity or controversy.  The timeframe for completion and certification of a full EIR is typically 12-15 months, although as noted above, projects in conformance with the 2020 LRDP can sometimes qualify for a less extensive process.  

Full EIRs are prepared by consultants under the direction of PEP staff; less extensive CEQA documents are often prepared by PEP staff. The cost of both staff and consultant time spent on CEQA documents is borne by the project budget.

The relationship of the CEQA process to the project approval process is shown in the Milestones table: the CEQA process depends on information about the project which is generated as the project develops, so the two must occur simultaneously.

CEQA documents for projects over $10 million must be certified by the Regents; projects $5 to $10 million are certified by UCOP, and those under $5 million by the campus. It is the campus practice to obtain certification of the CEQA documents before starting Working Drawings. Working Drawings are the most costly design phase, and there is significant risk to authorizing this work before the CEQA process is complete.  

close window to return to previous page