Projects $250K - $1M
Phase I Concept Approval

< $1M Review & Approval
- Review by SMCP
- Confirmation of Funding Source by VCUR/VCRPB
- CAPRA review/comment

< $250K
- Review and approval by VCAC

 |

$250K- $1M
- Review and recommendation made by VCAC approved by Chancellor

 |
Phase II Program Development Design & Working Drawings

< $1M Review & Approval
- Confirmation of professional services funding by VC Resource Planning & Budget
- If there are design and/or scope changes that impact the budget and/or schedule:
- Schedule revisions must be communicated to VCAC
- Funding plan submitted to VCAC

< $250K
- Review and approval by VCAC

 |

$250K - $1M
- Review and recommendation made by VCAC approved by Chancellor

|
Phase III Bidding and Construction

< $1M Review & Approval
- Budget augmentations due to high bids, cost overruns or scope changes require:
- Request must include source for additional funding

< $250K
- Review and approval by VCAC
|

$250K - $1M
- Review and recommendation made by VCAC approved by Chancellor
|
|
|
Projects Over $1M
Phase I Concept Approval

> $1M Review & Approval
- Review by SMCP
- Confirmation of Funding Source by VCUR/VCRPB
- CP approval preliminary budget/schedule
- CAPRA review/comment
- Review and recommendation for approval by ECPC
- Projects between $1-$5M may be delegated to VCAC review
- Approved by Chancellor

Phase II Feasibility Study

> $1M Review & Approval
- Confirmation of funding by VCUR/VCRPB & added to budget
- CAPRA review/comment
- Review and recommendation by DRC
- Review and recommendation by ECPC
- Approved by Chancellor

Phase III Program Development

> $1M Review & Approval
- Review and recommendation by DRC
- Confirmation of funding by VCUR/VCRPB & added to budget
- Review and recommendation by ECPC
- Approved by Chancellor

Phase IV Schematic Design Phase

> $1M Review & Approval
- Review by DRC, SRC, CCRAB
- Confirmation by V.C. Resource Planning & Budget
- Scope/budget/schedule changes require review and recommendation of Program Committee & ECPC
- Confirmation by SACI if scope change impacts Academic Effects Study
- Approval by Chancellor
- Submittal to OP of projects over $5 million for Design Approval
- Approved by Chancellor

Phase V Design Development Phase

> $1M Review & Approval
- Scope/Budget/Schedule changes require review and recommendation by CBC & ECPC
- Scope changes require Program Committee and SACI review
- Exterior design changes require review by DRC/ECPC
- Approved by Chancellor

Phase VI Working Drawing Phase

> $1M Review & Approval
- Scope/Budget/Schedule changes require review and recommendation by CBC & ECPC
- Scope changes require Program Committee and SACI review
- Exterior design changes require review by DRC/ECPC
- Approved by Chancellor

Phase VII Bidding and Construction Phase

> $1M Review & Approval
- Budget augmentations due to high bids, cost overruns or scope changes require review
and recommendation of VCAC
- Augmentation requests must include source for additional funding
- Approved by Chancellor
|
 |